Hohhot, capital of Inner Mongolia autonomous region, is committed to building a multi-mode transport system and has given priority to upgrading roads –– with a projected 127.63-kilometer network of new roads to be built before the end of 2018.

The construction of major projects including Sanhuan Road, Zhaowuda Road, Zhelimu Road, Bayanzhuoer Road and Jinhai Road are in full swing.

1025.jpg

A design sketch shows the view of Sanhuan Road. [Photo/hhhtnews.com]

With a total length of 82 km, Sanhuan Road is being constructed in three sections, which is helping to shorten the total construction period and guarantee the quality of the project. 

10252.jpg

Work continues on the Zhaowuda Road project. [Photo/hhhtnews.com]

Zhaowuda Road and Zhelimu Road will have a total length of 9.2 km. They are designed for vehicles traveling at speeds of up to 60 kilometers per hour.

10254.jpg

The construction site at Jinhai Road [Photo/hhhtnews.com]

Jinhai Road will run through Xincheng and Huimin districts, with a total length of 26 km. The new, two-way six-lane road will ease traffic pressures in the city.

"The construction work on Baiyanzhuoer Road is going smoothly," said Yun Ruipeng, vice-secretary of the commission for Huimin district.

He added that Baiyanzhuoer Road, which runs for 10.43 km, will form a north-south artery to facilitate transport in the city.

The projects are all expected to be completed by the end of 2018.